Sea Glass Construction Update

August 25 2025

We are excited to share the latest construction update for Sea Glass - August 2025
Sea Glass Construction Update

We’re pleased to report solid progress on site over the past month. Structural works to the basement levels are advancing steadily, marking the foundation of this prestigious half and full-floor apartment collection.

KEY MILESTONES

Completed:

  • Basement Pour: Successful pour of the Basement 3 slab
  • Lift core and fire stairwell: Basement 3 to Basement 2 reinforcement and concrete pours completed

In Progress:

  • Pile wall waterproofing: Waterproof membrane installation is underway on all exposed faces up to the capping beam
  • Shotcrete application: Ongoing to pile walls, now reaching 1 metre above Basement 2 slab
  • Basement columns: Reinforcement and formwork from Basement 3 to Basement 2 underway, with concrete pours continuing over the next week
  • Formwork: Preparation for Basement 2 slab now in progress
  • Basement 2 slab pour: Scheduled within the next three weeks
  • Tower crane installation: Due within the next four weeks, signalling a major milestone as the project begins to rise vertically.

 